We’ve got a lot of exciting capital project progress to share with you!
Crews have been hard at work in the Library and STEAM areas down at Attica Elementary, with demolition now completed in those spaces and cleanup underway.
Electrical teams are continuing important work on fire alarm systems, emergency lighting, data cabling, panels, transformers, and new equipment pathways at both the elementary and high schools.
Outside, the outdoor kitchen area has been graded and foundation work is moving forward for the new maintenance building. Footers have been poured, foundation walls are in place, and preparations are underway for upcoming concrete work at the outdoor kitchen.
We are grateful for the continued work of our construction teams and excited to see these projects take shape.
Thank you to our students, staff, families, and community for your patience and support as we continue improving our district facilities!
Crews have been hard at work in the Library and STEAM areas down at Attica Elementary, with demolition now completed in those spaces and cleanup underway.
Electrical teams are continuing important work on fire alarm systems, emergency lighting, data cabling, panels, transformers, and new equipment pathways at both the elementary and high schools.
Outside, the outdoor kitchen area has been graded and foundation work is moving forward for the new maintenance building. Footers have been poured, foundation walls are in place, and preparations are underway for upcoming concrete work at the outdoor kitchen.
We are grateful for the continued work of our construction teams and excited to see these projects take shape.
Thank you to our students, staff, families, and community for your patience and support as we continue improving our district facilities!